Auckland City remove 3 X 1000 Liter Tanks

When a 32 Story building in Auckland City wanted to remove 3 X 1000 Liter Tanks from the plant room on top of the building and install 7 X 340 liter water tanks They came to water works and asked us to design, and install the new installation

One requirement was to have hot water to all the apartments during this month long process

Process to install 7 x 340 liter hot water tanks, step by step.

Our Process

image001

1A. realign the boiler room door

image002

1A. Wall has been off set? We will remove the offset and make this wall flush, so the leaf of the door opens to 90 degrees Allowing old tanks to be removed and new tanks to be installed

image003

1A.The door to be moved so the wall is flush

image004

3B. Sprinkler heads to be removed where we are working

image005

3B. Sprinkler heads to be removed where we are working, hot works permitted work

image006

4A. Cold water pipe to have 4 new connections

image007

4A Hot pipe from gas heaters, 4 new connections needed

image008

4A Hot supply manifold 4 new connections to be made

image009

4 Tank to be removed and pipe work to be changed

image010

1B Position of 2 new 340liter hot water cylinders

image011

7. All old tanks to be cut up and removed

image012

4A. This cold water supply pipe will have to be turned off and more take off pipes added.

Photos of the New Tanks Are Shown Below

image018

Two tanks on the exterior of the main plant room

image019

5 new tanks installed, with new connections

image020

5 new tanks installed, with new connections

image021

New tanks with pipe work lagged